Minutes of Meeting In Board of Trustees
Trustees’ Capital Projects Committee Tuesday, January 7, 2003
A meeting of the Trustees’ Capital Projects Committee was
held in the Trustees’ Room of the Johnson Building at 10:00
a.m.
Present at the meeting were: Trustee Angelo M. Scaccia; President
Bernard A. Margolis; Alice Hennessey, Special Assistant to Mayor
Menino; Charles Worcester, Assistant Director, Division of Capital
Construction; P.A. d’Arbeloff, Communications Officer; Kathleen
Kirleis, Chief Financial Officer; Robert Flynn, Facilities Officer;
Edward Maheigan, Budget and Procurement Manager; and Jamie McGlone,
Clerk to the Trustees.
Chairman Angelo M. Scaccia presiding.
The first item on the order of business was the approval of Minutes
for the Trustees’ Capital Projects Committee Meeting on November
4, 2002. On a motion duly made and seconded, the Minutes for the
Trustees’ Capital Projects Committee Meeting on November 4,
2002 were approved.
Mr. Charles Worcester provided an update on the status and progress
of the McKim Restoration project, Phase IIC which has commenced
and will consist of the renovation of several significant public
spaces including the original Trustees’ Room; the Cheverus
Room; the Abbey Room; and the Sargent Gallery; in addition to the
restoration of the priceless murals by John Singer Sargent and Edwin
Austin Abbey.
President Margolis noted that the restoration work on the Sargent
Gallery murals and Cheverus Room by the conservators from Straus
Center for Conservation at the Harvard University Art Museums has
commenced and led the Committee members on a tour of the Sargent
Gallery and the Cheverus Room.
The project scope for McKim Restoration, Phase IIC also includes
the renovation of the McKim fifth floor, the installation of a new
elevator for greater accessibility to the Abbey Foyer, the installation
of a new book conveyor system, the installation of new restrooms
and the upgrading of the current restrooms, window restoration,
electrical and mechanical work, as well as furnishing of the McKim
Lobby and the original Trustees’ Room.
The architectural services for McKim Phase IIC are being provided
by Shepley, Bulfinch, Richardson & Abbott, Inc. The contractor
for the project is Lee Kennedy Company and the Straus Center for
Conservation at the Harvard University Art Museums is overseeing
the restoration of the McKim murals.
With regard to McKim Phase IIC project schedule and financing,
the construction for the next phase of the McKim project is estimated
to cost $14.3 million and is slated to be completed by May 2004,
including the background work on the heating, air conditioning,
mechanical and electrical portions of the project, in preparation
for the restoration of the Abbey and Sargent Gallery murals and
related building artwork.
On the financial front, funding for the project is in place at
the City Treasury and is estimated at a total project budget of
$20.4 million, including the transfer of the $7.5 million from the
State-funded match as a result of the City’s advance of $1.2
million, which has been fully reimbursed to the City of Boston.
The project budget also includes funding for architectural services
provided by Shepley, Bulfinch, Richardson & Abbott, Inc. coupled
with additional costs related to signage, artwork restoration, furnishings
and a contingency reserve fund.
President Margolis provided an update on the beginning planning
efforts for the next phase of the project, McKim Restoration project,
Phase IID. The President noted that the Library has begun internal
discussions and processes pertaining to the development of the project
scope for McKim Phase IID coupled with a preliminary review of the
capital funds which would need to be raised for the project.
The President reported that the project scope under consideration
for Phase IID will include the renovation of several significant
public spaces, including the Print Gallery, Music and Fine Arts
Departments, the Rare Books and Manuscripts Department, and the
Map Center on the McKim third floor.
While the project schedule and timetable has not yet been established
for Phase IID, they will be driven in part by fundraising efforts
and by Phase IIC’s projected completion date of May 2004.
In addition, the Library would anticipate seeking funding for Phase
IID with a heavy reliance on potential individual donors and federal
sources estimated at a total project budget of $25 million.
Ms. Alice Hennessey recalled that a wonderful presentation was
made by the Department of Neighborhood Development pertaining to
a study outlining what ideally would be needed to complete the McKim
Restoration project and asked that a copy of the report be shared
with Chairman Scaccia.
The President reported on the progress being made on the McKim
Map Room Café and Tea Room project noting that the Trustees’
Finance Committee, at its meeting tomorrow, would be provided with
an update on the proposed Café design development plans and
recommendation for a designated Library food services vendor.
On a separate but related topic, the President noted that the
proposed recommendations for improving the acoustics in both spaces
have been approved by the Landmarks Commission, along with other
changes to the McKim Map Room Café and Tea Room, which is
slated to be fully operational by early spring 2003.
In other ongoing Library capital projects, the President reported
on the progress being made on the South End Branch Library Window
Replacement project noting that the Division of Capital Construction
requested the general contractor terminate the contract with the
original sub-contractor for the new windows while the contractor
pursues the window replacements under a new contract.
The President also provided an update on the progress of projects
impacting eighteen different branches in various phases of capital
work, including the recent installation of iron gates for the two
exterior Courtyards at the Allston Branch Library. Meanwhile, work
is underway by the Division of Capital Construction on a number
of outstanding items remaining on the final punch list slated for
the new Branch Library.
On the awards front, the Allston Branch Library has been honored
with an award by the Boston Society of Architects and the New England
Association of the American Institute of Architects (AIA) and has
been recommended for an award from the National AIA, which the Hyde
Park Branch Library won in 2000.
Meanwhile, preparations are underway for exterior renovations
at the Codman Square, Grove Hall and Lower Mills Branch Libraries
which presently are in the design development phase with a projected
bid due date by mid February 2003. Further, renovations to the Roslindale
and South Boston Branches are also in the design development phase
with a projected bid due date in March 2003 and Roof Repairs at
Five Branches are in the design phase with an anticipated bid due
date early March 2003.
On the collaborative front, the Boston Public Library and the
Boston Parks Department are working in concert to address ADA accessibility
improvements at the Parker Hill Branch by having the entrance to
an unobtrusive handicapped access ramp start in the park adjacent
to the Library. To further that end, the project is in the design
development phase with a projected bid due date by early mid-May
2003.
In addition, the President noted that bids are due late winter
2003 for major roof repairs and ADA accessibility improvements at
the Connolly Branch Library while a projected due date of mid-February
2003 has been established for a variety of capital improvements
to the Faneuil and Jamaica Plain Branches, which will be funded
in part from a grant received from the Massachusetts Historic Commission.
Meanwhile, the preparation of working drawings is underway for
renovations earmarked for the McKim Basement/Flood Recovery project.
The contract is being amended to bring engineering on board to produce
the working drawings for the HVAC system required to support meeting
and event uses in a portion of the basement area with an anticipated
bid due date by March 2003.
On the Branch Library development front, the President reported
that the program work had been completed as part of the siting studies
for the Mattapan and Uphams Corner Branch Libraries by the firm
of Schwartz, Silver Architects, but in light of budgetary constraints,
the Library is not proceeding at this time with the site selection
work to identify potential sites for new branch libraries earmarked
for both communities.
Mr. Edward Maheigan shared with the Committee members a list of
the ongoing Critical Repair Fund Projects for FY 2003 reflecting
a total annual budget of $250,000 earmarked for smaller capital
projects not exceeding $25,000, including roof and bathroom repairs,
boiler replacements, environmental testing, and the installation
of sound attenuators in the Johnson building to reduce exterior
noise from the Library’s mechanical systems. To date, Mr.
Maheigan reported that critical repair capital projects totaling
$206,625.00 have been committed to or are in process for FY 2003.
Mr. Robert Flynn reported on a number of critical repair fund
projects successfully completed for FY 2003, including the emergency
repairs to the fire alarm electrical circuitry unit at the Dartmouth
Street entrance to the McKim building. Meanwhile, renovations to
the public and staff restrooms and front door replacements are underway
at several branch locations coupled with the near completion of
the installation of new boilers at every branch library.
Chairman Scaccia scheduled the next Trustees’ Capital Projects
Committee meeting for Tuesday, March 11, 2003 at 10:00 a.m. There
being no further business, the meeting of the Trustees’ Capital
Projects Committee adjourned at 12 noon.
Respectfully submitted,
Jamie McGlone
Clerk to the Trustees