Minutes
of the November 6, 2003 Meeting
A Minutes of Meeting
In Board of Trustees
Trustees’ Capital Projects Committee Thursday, November 6,
2003
A meeting of the
Trustees’ Capital Projects Committee was held in the Trustees’
Room of the Johnson Building at 10:00 a.m.
Present at the
meeting were: The Honorable Angelo M. Scaccia; President Bernard
A. Margolis; Alice Hennessey, Special Assistant to Mayor Thomas
M. Menino; Charles Worcester, Assistant Director, Division of Capital
Construction; Kathleen Kirleis, Chief Financial Officer; Ruth Kowal,
Director of Operations; P.A. d’Arbeloff, Executive Director,
the Boston Public Library Foundation; Robert Flynn, Facilities Officer;
Edward Maheigan, Budget and Procurement Manager; and Jamie McGlone,
Clerk to the Trustees.
Chairman Angelo
M. Scaccia presiding.
The first item
on the order of business was the approval of Minutes for the Trustees’
Capital Projects Committee Meeting on September 3, 2003. On a motion
duly made and seconded, the Minutes for the Trustees’ Capital
Projects Committee Meeting on September 3, 2003 were approved.
Mr. Charles Worcester
provided an update on the status and progress of the McKim Restoration
project, Phase IIC which has commenced with the renovation of several
significant public spaces including: the original Trustees’
Room. the Cheverus Room, the Abbey Room, the Sargent Gallery, and
the Exhibit Room located on the first floor of the McKim building.
In addition, the
restoration of the priceless murals by John Singer Sargent is progressing
by the conservators from Straus Center for Conservation at the Harvard
University Art Museums, which are slated to be completed by January
2004, along with renovation work to the Cheverus Room and the Edwin
Austin Abbey Room.
The project scope
for McKim Restoration, Phase IIC also includes the renovation of
the McKim fifth floor, the installation of a new elevator for greater
accessibility to the Abbey Foyer, the installation of a new book
conveyor system, the installation of new restrooms and the upgrading
of the current restrooms, window restoration, electrical and mechanical
work, as well as furnishing of the McKim Lobby and the original
Trustees’ Room.
The architectural
services for McKim Phase IIC are being provided by Shepley, Bulfinch,
Richardson & Abbott, Inc. and the contractor for the project
is Lee Kennedy Company.
With regard to
McKim Phase IIC project schedule and financing, the construction
for the next phase of the McKim project is estimated to cost $14.3
million and is slated to be completed by July 2004, including the
background work on the heating, air conditioning, mechanical and
electrical portions of the project, in preparation for the restoration
of the Abbey and Sargent Gallery murals and related building artwork.
On the financial
front, funding for the project is in place at the City Treasury
and is estimated at a total project budget of $20.4 million, including
the transfer of the $7.5 million from the State-funded match as
a result of the City’s advance of $1.2 million, which has
been fully reimbursed to the City of Boston. The project budget
also includes funding for architectural services provided by Shepley,
Bulfinch, Richardson & Abbott, Inc. coupled with additional
costs related to signage, artwork restoration, furnishings and a
contingency reserve fund.
Meanwhile, preliminary
planning efforts have commenced for the next phase of the project,
McKim Restoration project, Phase IID. To further those ends, the
Library has begun internal discussions, walk throughs, and processes
pertaining to the development of the project scope for McKim Phase
IID coupled with a preliminary review of the capital funds which
would need to be raised for the project.
The project scope
under consideration for Phase IID will include the renovation of
five primary public spaces, including the Print Gallery, Music and
Fine Arts Departments, the Rare Books and Manuscripts Department,
and the Map Center on the McKim third floor. The project scope and
related timetable for Phase IID will be crafted by utilizing the
Master Plan for the Central Library which was developed by Hardy
Holzman Pfeiffer Associates.
While the project
schedule and timetable have not yet been developed for Phase IID,
they will be driven in part by fundraising efforts and by Phase
IIC’s projected completion date of July 2004. In addition,
the Library would anticipate seeking funding for Phase IID with
a heavy reliance on potential individual donors and federal sources
estimated at a total project budget of $25 million.
Mrs. P.A. d’Arbeloff
noted that the fundraising strategy under consideration for Phase
IID would be to compartmentalize activities targeted to individuals
and constituencies who would have specific and particular interests
around the collections and services provided by the five primary
Library departments slated for renovation. Meanwhile, the 2004 Boston
Public Library Foundation Gala has been scheduled for Friday, May
7, 2004 in the McKim building to benefit the McKim Restoration project.
To further that
end, fundraising efforts for Phase IID have begun noting that the
City of Boston has granted permission for the Library to utilize
part of the funds raised by the Boston Public Library Foundation
through the Save America’s Treasures program to be earmarked
for Phase IID totaling $500,000. In addition, the Boston Public
Library is in receipt of a gift from an estate totaling $150,000
and the Foundation has submitted a grant proposal for $2.5 million
which will be slated for Phase IID.
In a review of
additional capital projects, President Margolis reported that the
Sebastians Map Room Café and Novel Restaurant renovation
projects have been successfully completed and that the food and
catering services operations have gotten off to a great start. The
two operations have received great reviews on both the quality of
food and on the ambiance of the renovated spaces. In addition, the
improvements to the acoustics in both spaces, which were approved
by the Landmarks Commission along with other changes, have proved
to be very successful particularly with the recent installation
of the new rug in the Café.
President Margolis
provided an update and status report on the progress of the Johnson
Building capital projects, including significant upgrades slated
for the Johnson Building Fire Alarm System, in which bids are expected
to be issued December 1, 2003 with construction scheduled to start
early winter 2004. Upon completion of the upgrades, while the Johnson
Building fire alarm system would remain separate from the McKim
fire alarm system, access to communication between both buildings
would be made available.
In other ongoing
Library capital projects, the South End Branch Library Window Replacement
project has been completed while additional branch repairs are expected
to be completed in November 2003. Meanwhile, the bids for the McKim
Basement Repairs and the Flood Recovery program are on track. The
bids were issued late October 2003 with a bid due date of December
1, 2003 with a project completion schedule within the five year
flood reconstruction timeline by August 2004.
President Margolis
distributed a capital projects update on the progress impacting
eighteen different branches in various phases of capital work and
reviewed their current project status. Among the projects highlighted,
Facilities Officer Robert Flynn reported that planning efforts are
underway for exterior renovations at the Codman Square, Grove Hall
and Lower Mills Branch Libraries noting that a contract has been
awarded with an anticipated project starting date on December 10,
2003.
Meanwhile, a construction
start date for renovations to the Roslindale and South Boston Branches
has been projected for November 2003. The current plan by the contractor
for the capital projects, BC Construction, is to complete renovations
to the Roslindale Branch first, then move to the South Boston Branch
phase of construction. Initial work at the Roslindale Branch will
focus on the skylight and roof followed by the installation of new
energy efficient windows.
On the collaborative
front, the Boston Public Library and the Boston Parks Department
are working in concert to address ADA accessibility improvements
at the Parker Hill Branch by having the entrance to an unobtrusive
handicap access ramp start in the park adjacent to the Library.
To further that end, the project is currently in the design development
phase in anticipation of going out to bid pending resolution of
financial issues.
On the Branch Library
development front, the President reported that the program statement
work has been completed as part of the siting studies for the Mattapan
and Uphams Corner Branch Libraries by the firm of Schwartz, Silver
Architects, but in light of budgetary constraints, the Library is
not proceeding at this time with the site selection work to identify
potential sites for new branch libraries earmarked for both communities.
On a related capital
planning issue, the Committee members discussed the need for the
development of an updated Master Facilities Strategic Plan for the
Boston Public Library branches, in light of the changing City demographics,
coupled with the City being besieged with requests for new Branch
Libraries, including a branch in Chinatown.
Meanwhile, a contract
has been awarded and construction is underway for major roof repairs
and ADA accessibility improvements at the Connolly Branch Library.
Further, preparations for Roof Repairs at five Branches, Brighton,
Dudley, East Boston, Egleston, and Orient Heights, are in process
and currently in the design phase with a bid due date of November
6, 2003, with construction projected to start early December 2003.
Mr. Flynn reported
that construction is currently underway and on track for a variety
of capital improvements to the Faneuil and Jamaica Plain Branches,
which is being funded in part with a grant received from the Massachusetts
Historic Commission. The renovations at both branches are primarily
focused on roof repairs, repointing and refurbishment of interior
surfaces while window replacements at the Faneuil Branch are slated
to be installed in January 2004.
On a related issue,
President Margolis recalled that the Secretary of State’s
Office wishes to impose deed restrictions on the Faneuil and Jamaica
Plain Branches in exchange for the $100,000 grant which would enable
the Massachusetts Historic Commission to dictate everything regarding
the future of the Branch Library buildings and sites.
The President said
that while there are deed restrictions on other City properties,
primarily held by the BRA, this would be an onerous request for
the Library. Meanwhile, the President noted that City officials
are reviewing the proposed deed restrictions language to determine
whether the Library would be able to request in a formal way a waiver
of all or part of this requirement.
Mr. Edward Maheigan shared with the Committee members a list of
the ongoing and completed Critical Repair Fund Projects for FY 2004
reflecting a total annual budget of $250,000 earmarked for smaller
capital projects not exceeding $25,000. Included among the critical
repair projects highlighted were roof and bathroom repairs, boiler
conversions from oil to gas, replacement lighting and wiring, environmental
testing, and the installation of sound attenuators in the Johnson
building to reduce exterior noise from the Library’s mechanical
systems.
Mr. Maheigan reported
that the Budget Office has allowed the Library to carryover $148,637
from the FY 2003 critical repair budget reflecting a total budget
of $398,637 available for FY 2004. To date, critical repair capital
projects totaling $350,821 have been committed to or are in process
for FY 2004.
Facilities Officer
Robert Flynn provided an overview of the critical repair capital
projects successfully completed for FY 2004 noting that the repairs
to the front doors of the West Roxbury Branch have been completed
along with the electrical upgrades and replacement lighting to the
Kirstein Business Branch. Meanwhile, bids will be issued this week
for a new handicap door at the South Street side entrance to the
Jamaica Plain Branch and a similar door for the front entrance to
the North End Branch.
In a review of
the critical repair projects slated for FY 2004, Mr. Flynn reported
that the following capital projects are underway: an oil tank removal
at the Parker Hill Branch due to a gas heating conversion project;
entry floor tile replacements at the Mattapan Branch; air conditioning
unit replacements at the Charlestown and Codman Square Branches;
repairs to the McKim Building’s Dartmouth Street platform
and marble flooring in the Courtyard; and repairs to the freight
elevator in the Johnson Building.
Mr. Flynn recalled
that mold was detected in the Central Library, Charlestown Service
building, and the New England Deposit Library facility resulting
from the high humidity this summer season. The mold clean-up at
NEDL, which involves the BPL and Harvard, will be covered by the
NEDL accounts while funds from the critical repair budget for FY
2004 will cover the ongoing clean-up at the Central Library and
the Charlestown Service building.
Ms. Kathleen Kirleis,
Chief Financial Officer, reported that the Library is in the process
of receiving resumes for the Capital Construction Project Manager’s
position at the Boston Public Library. Meanwhile, the CFO and Ms.
Ruth Kowal, Director of Operations, plan to begin interviewing potential
candidates this month in anticipation of filling the position by
the next Committee meeting.
Chairman Scaccia
scheduled the next Trustees’ Capital Projects Committee meeting
for Wednesday, January 6, 2004 at 11:00 a.m. President Margolis
then led the members of the Capital Projects Committee on a tour
of the McKim Restoration project, Phase IIC spaces. There being
no further business, the meeting of the Trustees’ Capital
Projects Committee adjourned at 12 noon.
Respectfully submitted,
Jamie McGlone
Clerk to the Trustees
|